Massport reveals schedule for summer runway work at Boston Logan
Posted: 29 May 2023 | | No comments yet
Massport announced the Runway 15R-33L Safety and Pavement Rehabilitation Project which is scheduled for this summer.


Massport's project will improve runway safety by enhancing the lighting and the surface conditions
The Massachusetts Port Authority (Massport) announced on 25 May 2023 the Runway 15R-33L Safety and Pavement Rehabilitation Project which is scheduled for this summer. In collaboration with the Federal Aviation Administration (FAA), Massport will begin work on Runway 15R-33L in August, with construction planned for approximately 100 days.
Serving as the longest runway at Boston Logan, Runway 15R-33L is primarily used by the FAA during northwest winds, which are typically prevalent in winter and spring months, and is the preferred late-night over Boston Harbor runway for noise abatement purposes. Runway 15R-33L was last rehabilitated in 2012.
Beginning August 14, Runway 15R-33L will be closed to all aircraft arrivals and departures. Consistent with FAA requirements, the project will improve runway safety by enhancing the lighting and the surface conditions. Work will be done in several phases to include the following:
- Replacing pavement and improving runway and taxiway intersections
- Upgrading electrical infrastructure
- Converting runway lights to energy efficient LEDs.
In addition to the runway rehabilitation elements, FAA recommended safety improvements will be made to several taxiway intersections to reduce the potential risk of aircraft runway incursions and to enhance airfield safety overall.
This August date was determined based on close coordination with the FAA and airline stakeholders while being mindful of the Sumner Tunnel closure. During the first few weeks of the closure, pavement will be removed and electrical elements will be installed. The majority of the pavement installation will occur in September and October..
Comprehensive mitigation measures will be put in place to reduce construction noise and other impacts to the surrounding communities. Those measures include:
- Reducing noise from truck back-up alarms within OSHA guidelines and other regulations
- Maximising daytime work, particularly noise producing activities
- Establishing airside haul routes that will maximise distance from neighbouring homes, particularly at night
- Hauling waste and other materials during the day to the extent possible
- Prohibiting trucks from using City of Boston streets to and from the airport
- All construction traffic will access the airport via Routes 90/93/1A and Coughlin Bypass Rd.
- Aiming all lighting used for night operations away from the communities
New report from International Airport Review: Securing Airports in an Evolving Threat Landscape
International Airport Review has brought together top voices from across the global aviation security sector, including International Civil Aviation Organization (ICAO), ACI World, Fraport, Qatar Civil Aviation Authority, Winnipeg Airports Authority, and Smiths Detection to examine today’s most pressing airport security challenges and emerging threats.
This expert-led report provides a strategic assessment of the vulnerabilities facing airports in 2025, encompassing cyber-attacks, drone incursions, evolving geopolitical risks, and emerging technologies.
The result is a practical, insightful guide to strengthening airport resilience, anticipating risks before they escalate, and keeping your airport off the front page
Download the report for free and stay ahead of the security curve – READ FOR FREE NOW!
Related topics
Airport construction and design, Runways and pavements, Social responsibility, Sustainability, Terminal operations
Related airports
Related organisations
Federal Aviation Administration (FAA), Massachusetts Port Authority (Massport)