Los Angeles Board of Airport Commissioners awards construction contract for rehabilitation of Van Nuys Airport’s main runway 16R

0
SHARES

Posted: 15 October 2012 | Van Nuys Airport | No comments yet

BOAC approved a $13,908,464 contract…

Los Angeles World Airports Logo

Today, the Los Angeles Board of Airport Commissioners (BOAC) approved a $13,908,464 contract to Security Paving Company, Inc., for rehabilitation of the main runway (16R/34L) at Van Nuys Airport (VNY). The total amount of the project, which includes all cost elements, is estimated at $20,483,076. Ninety percent of the project’s cost will be funded through a Federal Aviation Administration (FAA) grant.

Runway 16R stretches 8,000 feet and is one of two runways at VNY, ranked as one of the nation’s busiest general aviation airports. The project, which includes the rehabilitation of 6,800 feet of asphalt pavement using a combination of asphalt overlay and partial pavement reconstruction, will be phased over three sections of the runway (north, south and center). The project also includes the widening of existing runway shoulders to meet FAA design standards, along with improvements to the aircraft run-up area and repairs to existing, concrete runway pavement.

Through a collaborative effort among airport management and tenants, the rehabilitation project has been designed to minimize operational impacts and maximize improvements to the airfield complex. “VNY plays an integral role in our nation’s air transportation system and is a vital contributor to the Southern California economy,” said VNY Airport Manager, Jess Romo. “It’s a great example of collaboration among key stakeholders in an effort to minimize operational impacts and help preserve the airport’s status as one of the world’s premier general aviation facilities.”

 secure your free spot 

 


Accelerating the energy revolution in airports

25 February, 2026, 02:00PM GMT

This webinar will provide actionable knowledge for airport operators and their sustainability leaders seeking to accelerate their transition towards a low-carbon future.

Key learning points:

  • Understand how airports are deploying on-site renewable energy and storage solutions to reduce carbon emissions
  • Learn best practices for electrifying airside and landside operations, including ground support equipment
  • Gain insights into preparing infrastructure for hydrogen and sustainable aviation fuel integration

REGISTER NOW TO GAIN EXPERT INSIGHTS

During project work, VNY will operate with a shortened runway length for 65 days, with no less than 5,000 feet available for arrivals and 5,209 feet available for departures. Full runway closures will be limited to 10 days. A series of 26 night closures occurring from 10 p.m. to 6 a.m., will take place prior to and after the 24-hour closure dates. Operations on the airport’s 4,000-foot parallel runway will not be impacted.

With today’s BOAC action, Los Angeles World Airports’ staff anticipates work to commence in November 2012 with completion by the end of August 2013.

 


SIGN ME UP

 

Stay Connected with International Airport Review — Subscribe for Free!

Get exclusive access to the latest airport and aviation industry insights from International Airport Review — tailored to your interests.

Expert-Led Webinars – Gain insights from global aviation leaders

Weekly News & Reports – Airport innovation, thought leadership, and industry trends

Exclusive Industry Insights – Discover cutting-edge technologies shaping the future of air travel

International Airport Summit – Join our flagship event to network with industry leaders and explore the latest advancements

Choose the updates that matter most to you.

Sign up now to stay informed, inspired, and connected — all for free!

Thank you for being part of our aviation community. Let’s keep shaping the future of airports together!

Send this to a friend