TAV Airports has completed a €29 million modernisation of the domestic terminal at Almaty Airport, raising annual capacity to more than 8 million passengers.

AlmatıAcılıs

Almaty Airport domestic terminal modernisation completed

Credit: TAV Airports

TAV Airports, a member of Groupe ADP, has completed the modernisation of the domestic terminal (T1) at Almaty Airport (ALA) in Kazakhstan, a €29 million project that lifts the terminal’s annual passenger capacity to more than 8 million.

The renovated terminal was inaugurated at a ceremony attended by Asel Zhanassova, Deputy Prime Minister and Minister of Transport of Kazakhstan, Darkhan Satybaldy, Akim of Almaty, and Serkan Kaptan, CEO of TAV Airports. Work began in September 2025 and was completed in 13 months without disrupting terminal operations.

Check-in, security and baggage capacity expanded

The project covered upgrades to check-in, security screening, baggage handling and passenger waiting areas. The 1,700-square-metre check-in area was renovated and 23 new counters were installed. The security screening area was expanded by 200 square metres, and a new computed tomography (CT) screening system providing three-dimensional imaging was introduced at security checkpoints.

The number of automated boarding pass control gates increased from three to five, passenger waiting areas at eight boarding gates were renovated and three new passenger boarding bridges were installed. The terminal’s electrical, ventilation, heating and fire safety systems were also completely renewed.

Baggage handling capacity was increased. The outbound baggage sorting area was expanded from 1,000 to 1,800 square metres, while the baggage reclaim area grew from 964 to 1,891 square metres. Conveyor belt length rose from 85 to 228 metres, and hourly capacity increased from 990 to 1,680 pieces for departures and from 1,380 to 2,250 pieces for arrivals.

The Extime lounges operated by TAV Operation Services were completely renovated. The 750-square-metre departure lounge accommodates 110 guests and includes dining and relaxation areas, a meeting room, a private VIP room and prayer rooms. The 250-square-metre arrivals lounge has a capacity of 22 guests.

Kaptan said: “We continue to invest in Almaty Airport to strengthen its position as one of Central Asia’s leading aviation hubs. In 2024, we inaugurated the new international terminal. We have now completed the modernisation of the domestic terminal in just 13 months.”

TAV Airports began operating Almaty Airport in 2021, when it handled 6 million passengers. Traffic reached 11.9 million in 2025, and the airport was named among the “World’s Top 100 Airports” in the Skytrax awards in the same year.

The first investment programme, totalling €257 million and including the new international and VIP terminals, was completed in 2024. A second phase worth €315 million is scheduled for completion by the end of 2027, which would bring total investment in the airport to approximately €572 million.

Beyond the domestic terminal, the second phase includes Central Asia’s first dedicated aircraft de-icing area and a new 4,000-metre taxiway. Plans also cover resurfacing one of the runways with concrete pavement, upgrading the VIP apron and aircraft parking areas, expanding the cargo apron and constructing a new aircraft maintenance hangar.

Almaty Airport serves as the hub for Air Astana, Kazakhstan’s flag carrier. At the end of 2025, 42 airlines operated flights from the airport to 86 destinations across 30 countries.

Kaptan added: “We will continue to contribute to Almaty’s development as a major transfer hub in Central Asia.”