news

East Midlands Airport announces runway refurbishment project

Posted: 23 August 2016 | Katie Sadler, Digital Content Producer | No comments yet

East Midlands Airport has announced it will be undertaking full length runway refurbishment during November and December 2016.

East Midlands Airport announces runway refurbishment project

East Midlands Airport has announced it will be undertaking full length runway refurbishment during November and December 2016.

East Midlands Airport announces runway refurbishment project

The refurbishment will be completed over seven consecutive weekends, a UK first for airport runway refurbishment projects, meaning that the airport will be closed to all traffic for 48 hours each weekend. The closures will begin at 20:00hrs on each Saturday and end at 20:00hrs on each Monday, except the final weekend, which will end at 13:00hrs.

A UK first: runway refurbishment completed over seven consecutive weekends

Andy Cliffe Managing Director East Midlands Airport said: “After an in depth consultation with our airlines and cargo operators, we came to the decision that completing the project in this way was the best way to avoid major disruption in the lead up to Christmas. The timing for us is crucial and we had to look to do this in the winter season, when we naturally aren’t as busy.”

Beginning on 5th November 2016 and concluding on 19th December 2016, the project will see around 360 workers every weekend laying 50,000 tonnes of specially formulated material across 150,000m2 in total.

Whilst the runway is not operational, the airport is also replacing over 1200 lights on and around the area with LED lighting, which is more environmentally friendly.

The airport’s runway was last refurbished in 1999, and has a natural lifespan of around 12-17 years. Galliford Try is the principle contractor and has worked together with the management and operations team at the airport to ensure that the airport’s operation has minimal disruption.

Colin Abbott, Aviation Director for Galliford Try said: “We are delighted to be working with the East Midlands Airport team on the refurbishment of their Runway.  Logistics make this an exceptionally challenging project and due to the hard work of all involved scoping out every possible scenario, we have every confidence that the scheme will be delivered safely and on time.”

Andy Cliffe continued: “We’re delighted to be working with Galliford Try; they are a leading construction company and have a great deal of experience in managing a large scale project like this.

“We are very much looking forward to seeing the work taking place in this exceptional way and then seeing the finished product in December.”